偏压隧道抗滑桩回填反压失效原因分析及处治措施
引用本文:苟德明,邓少军.偏压隧道抗滑桩回填反压失效原因分析及处治措施[J].中国科技信息,2010(6):55-58.
作者姓名:苟德明  邓少军
作者单位:贵州省交通规划勘察设计研究院,550001
摘    要:在某软弱围岩偏压隧道中采用抗滑桩回填反压作为抗偏压措施,但在隧道施工过程中因洞内坍塌引起仰坡滑移开裂及支护结构变形破坏,本文分析了抗滑桩回填反压失效原因,并结合现场实际情况采用了相应的处治措施,使隧道施工顺利进行,为类似工程总结了经验和教训.

关 键 词:偏压隧道  软弱围岩  抗滑桩  回填反压  失效

Failure Reason Analysis and Treatment Measures of Counter-pressure Filling with Anti-slide Piles in Unsymmetrical Pressure Tunnel
Gou Deming,Deng Shaojun.Failure Reason Analysis and Treatment Measures of Counter-pressure Filling with Anti-slide Piles in Unsymmetrical Pressure Tunnel[J].CHINA SCIENCE AND TECHNOLOGY INFORMATION,2010(6):55-58.
Authors:Gou Deming  Deng Shaojun
Institution:Gou Deming Deng Shaojun Guizhou Communication Planning , Prospecting Design Academy,Guiyang 550001,China
Abstract:The counter-pressure filling with anti-slide piles,as an anti-unsymmetrical pressure measure,was used in a soft surrounding rock and unsymmetrical pressure tunnel.But the slip crack of tunnel heading slope and the deformation failure of supporting structure were caused by cave collapse during the tunnel construction.The failure reasons of counter-pressure filling with anti-slide piles were analyzed in this paper and the corresponding treatment measures were applied in combination with on-site practice condi...
Keywords:unsymmetrical pressure tunnel  soft surrounding rock  anti-slide pile  counter-pressure filling  failure  